Moreno Valley Sewer Improvement Project
Moreno Valley, California

The Eastern Municipal Water District retained Christensen Brothers General Engineering to construct 2,000 feet of 21-inch-diameter sewer pipe in Moreno Valley.  As part of the work, the contractor was required to install ground movement monitoring sensors adjacent to an existing residence.  Christensen Brothers hired Geocon to install the monitors.


Interesting Fact: Eastern Municipal Water District treats 46 million gallons of wastewater each day

Client
Christensen Brothers General Engineering

Owner / Agency
Eastern Municipal Water District

Services
Instrumentation

Geocon Leaders
Gerry Kasman, CEG